HVAC TAB Procedure

TAB tests, adjusts and balances HVAC flows and conditions. Follow the sequence from preparation to measurement and reporting.

Measured ItemsWhat TAB measures

Record design values, measured values and operating conditions
ItemMeasurementsKey conditions
Airflow and velocityAHU, duct and supply/return/exhaust terminal flows and distributionOperating mode, fan speed, damper position and filter condition
Static pressureStatic pressure and pressure losses at fans, ducts and filtersTap location, airflow and instrument range
Differential pressureRoom differentials and intended airflow directionDoor state, leakage and supply/exhaust combinations
Temperature and humiditySupply/return/room temperature and relative humidityOutdoor, equipment and occupancy loads, stabilisation time and measurement positions
Water flow and equipment operationApplicable chilled/hot-water flows, pressure and pump/fan operationApply to systems included in the agreed scope

Tolerances come from the contract specification, design documents and approved test plan. Do not apply one ±% to every item or change acceptance criteria after measuring.

ProcedureTAB procedure

From preparation to final checks
StageWorkRecords and results
1. Design review and planDefine systems, design flows/pressures, operating modes, tolerances, test points and instrumentsTAB plan, design-value register and measurement forms
2. Installation readinessCheck ducts, pipes, filters, dampers, valves, sensors and access; verify rotation and controlsReadiness checklist and resolved/open items
3. Initial measurementsMeasure system, branch and terminal baselines under design operating conditionsRaw pre-adjustment flow, pressure and temperature/humidity readings
4. Adjust and balanceAdjust fans/pumps, branches and terminals in sequence and remeasure interactionsFinal positions, speeds, set points and repeat readings
5. Final verification and reportCheck deviations by mode, room pressure/temperature/humidity and agreed alarm/changeover functionsFinal report, marked-up drawings, deviations and outstanding items

DeliverablesTAB report contents

Record system and equipment IDs, drawing/specification revisions, design/measured values, deviations and conclusions, instrument IDs and calibration validity, measurement positions/time/operating conditions and before/after adjustment readings. Trace any shortfall through its cause, action and remeasurement.

Hand over final damper/valve positions and control settings on drawings and schedules. Identify the zones affected by changes and define the checks needed after extensions, filter replacement or operating-mode changes.

IQ / OQHow TAB relates to IQ and OQ

TAB commissions and measures the design operating points; it does not itself complete GMP qualification. IQ checks installation, materials, calibration and documentation against the approved design; OQ verifies operating ranges, alarms and functions against protocol criteria.

To use TAB results as qualification evidence, review methods, instruments, criteria and raw-data traceability and link them to an approved protocol before testing. Document the required tests, deviations and retesting. (EU GMP Annex 15, section 3)

SAMYOUNG ENG supports IQ/OQ documentation and testing and TAB for GMP facilities, using its own airflow meters, anemometers, a particle counter, digital temperature/humidity meters, an electronic flowmeter and a temperature recorder.

FAQFrequently asked questions

Frequently asked questions

What does TAB stand for?

Testing, adjusting and balancing. It brings HVAC air/water flows and environmental conditions to the design requirements and documents the final measurements.

Does completing TAB finish OQ?

No. TAB is commissioning; OQ documents tests of operating ranges, functions and alarms under an approved protocol. Suitable TAB raw data may be used as evidence after review and approval.

Is TAB needed after filter replacement?

Changed filter resistance can affect airflow and room pressure. Define remeasurement and rebalancing from the change impact and plan any required requalification for GMP facilities.